Road resurfacing schedule

July and August 2018

The list of roads scheduled for resurfacing and traffic management requirements are as follows. All timings are weather dependent.

  • London Street - Junction Queen's Road to Junction London Road (Katesgrove Ward) Start Monday 16th July expected to take up to 5 nights. Working hours 7.00 pm to 1.00am. Full road closure with a signed diversion route.
  • Duke Street - Junction Queen's Road to Zebra Crossing Vicinity (Abbey Ward) Start Thursday 19th July expected to take 2 nights working 7.00 pm to 1.00 am. Full road closure with signed diversion.
  • Bridge Street - IDR to Fobney Street (Abbey Ward) Start Monday 23rd July expected to take up to 5 nights. Working hours 7.00 pm to 1.00 am. Full Road closure with signed diversion route.
  • Park Lane - Junction Halls Road to Junction City Road (Tilehurst Ward) Start Wednesday 25th July expected to take 2 days. Working hours 9.30 am to 3.30 pm. Full road closure with signed diversion.
  • City Road - Junction Park Lane to Borough Boundary (Tilehurst Ward) Start Thursday 26th July expected to take 1 day. Working hours 9.30 am to 3.30 pm. Full road closure with signed diversion.
  • Burghfield Road - Junction Bath Road to Old Kennels Court (Southcote Ward) Start Friday 27th July expected to take 5 days. Working hours 9.30 am to 3.30 pm. Full road closure with signed diversion.
  • Caversham Park Road - Junction Birchwood Close to Junction Northbrook Close (Peppard Ward) Start Monday 30th July expected to take 2 days. Working hours 9.30 am to 3.30 pm. Full road closure with signed diversion.
  • Redlands Road - House No 24 to Junction London Road (Redlands Ward). Start Wednesday 1st August expected to take 2 days working 9.30 am to 3.30 pm. Full road closure with signed diversion.
  • Wigmore Lane/Portman Road - Junction Stone Street to Junction Bridgewater Close (Kentwood Ward) Start Monday 6th August expected to take 3 nights working 7.00 pm to 1.00 am. Full road closure with signed diversion.
  • Oxford Road - Westbound from Reading Retail Park to Norcot Road Roundabout (Norcot Ward) Start Thursday 9th August expected to take 1 night working 7.00 pm to 1.00 am. Lane closures with Traffic Management. 
  • Southampton Street - Junction Pell Street to Junction Crown Street (Katesgrove Ward) Start Friday 10th August expected to take 4 nights working 7.00 pm to 1.00 am. Full road closure with signed diversion.
  • Rose Kiln Lane - Junction Admiral Court to Junction Berkeley Avenue (Minster Ward) Start Monday 13th August expected to take 3 days working 9.00 am to 5.00 pm. Full road closure with signed diversion.